Traffic Management

Printer-friendly version

 

Current Roadworks - Temporary Road Closures - Bridge Closures

The Samuel Beckett Bridge will close to both pedestrian and vehicular traffic on the following dates to facilitate the Three Bridges Liffey Cruise.
 
  • Tuesday, 19th February 2019, from 21.00 hours to 22.00 hours

    Please click here to view a schedule of planned bridge closures up to and including 30th April 2019.

_________________________________________________________________________________________________________________________

Benson Street and Green Street East, Dublin 2
 

John Sisk & Sons intends to close the following road to facilitate drainage and water supply works on the dates and times listed below:
•Benson Street and Green Street East, Dublin 2 from 00.00hrs on Monday 12th March 2018 to 24.00hrs on Friday 30th November 2018.
•This temporary road closure was due to end at 24.00hrs on Friday 1st June 2018 but has now been extended due to unforeseen circumstances.

Traffic Management Plan
•Pedestrian and local access will be maintained.
 

Hanover Quay, Dublin 2


John Sisk & Son (Holdings) Ltd intends to close the following road to facilitate cobble reinstatement on the dates and times listed below:
•Hanover Quay, Dublin 2 from 00.00hrs on Monday 14th January 2019 to 24.00hrs on Friday 15th February 2019.

Traffic Management Plan
•Pedestrian and local access will be maintained.

 

Sheriff Street Upper, Dublin 1.


Kavanagh Crane Hire Ltd intends to close the following road to facilitate tower crane dismantling works on the date and times listed below:
•Sheriff Street Upper (from North Wall Avenue to East Wall Road), Dublin 1 from 06.00hrs to 19.00hrs on Sunday 3rd March 2019.

Traffic Management Plan
•Access to Dublin Port Terminal 3 will be maintained.
•Traffic on Sheriff St Upper wishing to travel to East Wall Road will be diverted via North Wall Avenue and North Wall Quay.
•Traffic on East Wall Road wishing to travel on Sheriff St Upper will be diverted via North Wall Quay and North Wall Avenue.
•Pedestrian and local access will be maintained.


Benson Street, Dublin 2.

Architectural Aluminium Ltd. intends to close the following road to facilitate crane Lift operations on the dates and times listed below:
•Phase One:     From 06.00hrs to 18.00hrs each day on Saturday 16th February 2019 and Sunday 17th February 2019.
•Phase Two:     From 06.00 to 18.00hrs each day on Saturday 2nd March 2019 and Sunday 3rd March 2019.

Alternatively, or as ‘Back Up dates’ proposed below:           
•Phase One:     From 06.00hrs to 18.00hrs each day on Saturday 23rd February 2019 and Sunday 24th February 2019.
•Phase Two:     From 06.00hrs to 18.00hrs each day on Saturday 9th March 2019 and Sunday 10th March 2019.

Traffic Management Plan
•Pedestrian and local access will be maintained.


 



 


 

 

 
 
 

 